Principal designer duties under CDM 2015
A plain-English guide for clients, designers and contractors, with the regulation reference for every point so you can check the source.
When must a principal designer be appointed?
Where there is more than one contractor, or it is reasonably foreseeable that more than one contractor will be working on a project at any time, the client must appoint in writing a designer with control over the pre-construction phase as principal designer (reg 5(1)(a)). The client must also appoint a principal contractor (reg 5(1)(b)).
The appointments must be made as soon as is practicable, and in any event before the construction phase begins (reg 5(2)).
What if the client doesn't appoint one?
If the client fails to appoint a principal designer, the client must fulfil the principal designer's duties in regulations 11 and 12 itself (reg 5(3)).
What does the principal designer do?
- Plan, manage and monitor the pre-construction phase, and coordinate health and safety matters during it, so that, so far as is reasonably practicable, the project is carried out without risks to health or safety (reg 11(1)).
- Take account of the general principles of prevention when design, technical and organisational aspects are decided and when estimating how long work will take (reg 11(2)).
- Identify and eliminate or control foreseeable risks, so far as is reasonably practicable, to anyone carrying out or affected by construction work, maintaining or cleaning the structure, or using a structure designed as a workplace (reg 11(3)).
- Make sure all designers comply with their duties in regulation 9 (reg 11(4)).
- Make sure everyone working on the pre-construction phase cooperates with the client, the principal designer and each other (reg 11(5)).
- Assist the client with pre-construction information, and provide it promptly to designers and contractors, so far as it is within the principal designer's control (reg 11(6)).
- Liaise with the principal contractor and share information relevant to the construction phase (reg 11(7)).
- Help the principal contractor prepare the construction phase plan by providing relevant information it holds (reg 12(3)).
- Prepare the health and safety file during the pre-construction phase, and keep it reviewed and updated (reg 12(5) and (6)). At the end of the project, the file passes to the client (reg 12(10)).
Related client duties
- Make suitable arrangements for managing the project, including sufficient time and other resources (reg 4(1)).
- Provide pre-construction information as soon as practicable to every designer and contractor appointed or being considered for appointment (reg 4(4)).
- Take reasonable steps to ensure the principal designer complies with its duties (reg 4(6)(a)).
- Notify the Health and Safety Executive in writing before the construction phase begins if the project is notifiable: construction work scheduled to last longer than 30 working days with more than 20 workers working simultaneously at any point, or to exceed 500 person days (reg 6(1) and (2)).
Not the same as the Building Regulations principal designer
The Building Regulations 2010 (Part 2A) use the same role names, but the duties are separate. One organisation can hold both roles, but each appointment must be made in its own right.
Need a principal designer?
QMS Technology Ltd provides CDM Principal Designer services. Email hello@qmstech.co.uk to request a fee proposal.
Working on a higher-risk building in England? See our free Gateway 2 Readiness Scorecard.
General information, not legal advice. Always check the current legislation and HSE guidance.